ולידציה – Validation case study – part 2

ולידציה – Validation case study – part 2

 This article was written by Iian Shaya, validation,automation and control expert

Validation Requirements

Documentation for Initial Tender

Project schedule and milestones design and construction detail

Project quality plan

Supplier’s local subsidiary/agent

Supplier’s documentation that the system / configurable software versions are released to the market and are FDA/EMEA compliant

Compliance to the 21 CFR Part 11 operational requirements – the contractor should ensure covering of all the requirements described below

Contractor to state the system/product status and implementation planned for each requirement – User's approval pre-delivery

Documentation for Design Review

PID for the system

Electrical and pneumatic schematics

:Installation data

General arrangement drawings

Floor loading

Utility requirements

Details of electronic records and approvals that may be subject to regulatory controls under CFR Title 21 part 11

Instrumentation documentation

:Main components specification

Equipment

Instrumentation

Valves

Piping

Control system

Pipe welding documentation

General installation book

Procedures

User guide

Security

Preventative maintenance + spare parts list

Operation procedure

Pressure test procedure

Leak test procedure

Passivation procedure

Calibration

:Functional Design Specifications for

Complete manufacturing system

Software – SW and hardware –HW

Functional Design Specifications

System Detail Design Specifications for HW and SW.

SW source code, with comments, for customized SW

SW complete version history

HMI alarm list, message list and graphical displays

I/O list

:List of materials

Product contact materials

Potential product contact lubricants

Welding procedures for product direct and indirect contact parts

Pre-delivery Inspection and Factory Acceptance Test (FAT) protocols

Steel certificates and gasket certificates

Documentation Prior to FAT or Pre-Delivery Inspection – PDI

:Progress visit report which will include

Mechanical and technical development

Automation and SW development

:Supplier’s factory test results for

Unit tests – The test protocols shall be traced to low level design document and will be approved by the user prior to execution. The approval of the report shall be performed by representatives of the user's validation team, IT QA.

Automation and SW development

:Integration Tests  – Simulation Testing

Approved PDI and FAT protocols

Commissioning

MCCR

Purpose

Scope

Responsibility

Execution instructions

System scope

System description

Drawing verification

Equipment verification

Valve verification

Instrument installation and calibration

Utility verification

Documentations verification

Piping Verification

Sample Point Verification

Safety, health and environment verification

Slopes verification (if relevant)

Electrical and communication activities

Pump installation verification, if relevant

Heat exchanger installation verification, if relevant

Air break verification, if relevant

Dead leg verification, if relevant

CE

Purpose

Scope

Responsibility

Execution instructions

System scope

System description

System startup

Equipment verification

Main equipment operation checks

System FDS (SSO) verification

System performance testing

 This article was written by Iian Shaya, validation,automation and control expert